JULY 2009 Monthly Progress Report
(Rs. in lakhs)  
Sl Name of Schemes Total Date of Target Progress   Grand Balance If project is behind
No.   Sanctioned Commence- Date of Physical Financial Total fund schedule resons
    Cost ment Completion in % (Rs. Edpdt. ruquired thereof /
    (Rs.in lakhs)       in lakhs)   (Rs.in lakhs) Remarks
1 2 4 5 6 7 8 9 10 11
  NABARD  SCHEMES                
1 Augmentation of Tashiding Bazar Water Supply Scheme 261.21 15.12.07 14.12.08 70% 136.12 136.12 125.09 Work under Progress
2 Augmentation.of Hee Bermiok Bazar Water Supply Scheme 102.00 10.9.07 9.03.07 88% 70.40 70.40 31.60 Work under Progress
3 Improvement of intake structure, shifting and replacement of 4" dia GI Pipe line from Rehsi Khola source for Kaluk - Rinchenpong W/S/S 79.83 1.08.07 31.1.08 100% 80.23 80.23 -0.40 Work Completed
4 Construction of Sedimentation Tank at Naya Bazar W/S Scheme 22.92 6.9.07 7.6.08 98% 15.21 15.21 7.71 Work under Progress
5 Augmentation of Mangalbaria W/S Scheme in West Sikkim 258.98 6.4.07 29.12.08 80% 189.23 189.23 69.75 Work under Progress
6 Augmentation of Reshi Water Supply Scheme 264.00  --  -- 10% 28.91 28.91   Work under Progress
7 Providing W/S to Debrung, Dhambudara and Kamrang in Namchi 220.58 ------ ------ 10% 15.00 15.00 205.58 Work under Progress
8 Providing 2 unit gravity pressure filter & re-alignment of dist.line  for Charcharey source, Jorethang W/S System 53.58 ------ ------ 25% 17.14 17.14 36.44 Work under Progress
9 Augmentation.of Darap Water Supply Scheme, West Sikkim 246.60     10% 0.00 0.00 246.60 Work under Progress
10 Augmentation of Rangpo W/S by lifting from Rangpo Khola 135.58 6/2/2002 9/2/2005 60% 98.63 98.63 36.95 Work held up due to washout of the site & materials by flood of Rangpo Khola
11 Const. of 198cum reservoir above Milk Dairy 5th Mile, Tadong 10.12 6/8/2007 9/7/2007 97% 2.75 7.36 2.76 Work under Progress
12 Rorathang Water Supply Scheme in East Sikkim 520.35 8.9.08 7.9.2010 48% 70.43 70.43 449.92 Work under Progress
13 Augmentation of Singtam(RMC) W/S Scheme in East Sikkim 459.62 18.4.08 12.4.09 75% 420.99 420.99 38.63 Work under Progress
14 Const. of W/S Scheme at Middle Camp in East Sikkim 319.51       72.26 72.26 247.25 Work under Progress
15 Const. of W/S Scheme at Shekwa Bazar in East Sikkim 76.15       11.52 11.52 64.63 Work under Progress
  Total ::: 2635.37       1145.04 1149.65 1250.63  
  B.A.D.P. SCHEMES            
1 Providing Water Supply to Trade Mart at Sherathang 338.00 16.4.2007 15.3.2007 100% 61.78 61.78 276.22 Work completed
3 Augmentation of Bitchu Water Supply Scheme 50.00 18.4.2007 17.4.2008 90% 47.76 47.76 2.24 Work under progress
4 Augmentation of Drinking W/S at Lachung, North Sikkim 358.00 24.7.07 23.10.07 95% 295.52 343.58 14.42 Work under progress
5 Augmentation of Yuksum Water Supply Scheme. 150.00 9.9.2005 1.7.2007 100% 141.12 141.12 8.88 Work completed
  Total ::: 896.00       546.18 594.24 301.76  
  NLCPR SCHEMES          
1 Augmentation  of Gyalshing Water Supply Scheme. 752.28 10.01.2005 31.03.2007 99% 712.85 712.85 39.43 Work under Progress, likely to be completed
2 Augmentation of W/S Scheme for greater Rangpo in East Sikkim 1699.95 25.4.2007 24.4.2008 83% 1694.20 1694.20 5.75 Work Under Progress
3 Construction of Water Supply Scheme at Sang Naya Bazar 206.72  ----  ---- 50% 119.83 131.32 75.40 Work Under Progress
4 Augmentation of Rhenock W/S Scheme in East Sikkim 1627.31 12.9.08 11.9.2010 30% 681.60 681.60 945.71 Work Under Progress
  Total ::: 4286.26       3208.48 3219.97 1066.29  
(Rs. in lakhs)  
Sl Name of Schemes Total Date of Target Progress   Grand Balance If project is behind
No.   Sanctioned Commence- Date of Physical Financial Total fund schedule resons
    Cost ment Completion in % (Rs. Edpdt. ruquired thereof /
    (Rs.in lakhs)       in lakhs)   (Rs.in lakhs) Remarks
1 2 4 5 6 7 8 9 10 11
  NEC SCHEMES              
1 Kaluk - Rinchenpong W/S Scheme. 350.00 10.2.2004 31.03.2007 100% 346.47 346.47 3.53 Work completed
2 Providing distribution Reservoir & distribution  main trunk lines for Namchi W/S System to Namchi Town. 432.76 17.11.2006 16.5.2007 100% 351.64 351.64 81.12 Work completed
3 Const. of security fencing approach road, parking yard compound lighting at Selep WTP 211.79 10.2.2004  --- 100% 201.67 201.67 10.12 Work completed, final payment to be made
4 Extension of sewerage system in and around Gangtok, Phase - III 420.51 10.2.2004  --- 100% 399.64 399.64 20.87 Work completed, final payment to be made
5 Providing new distribution network system for W/S to Namchi town PH-II 443.50  ---  --- 35% 53.98 53.98 389.52 Work Under Progress
6 Strengthening of Distribution system of Pakyong W/S in East Sikkim. 229.71 10.8.2006 12.2.2007 100% 227.51 227.51 2.20 Work completed
7 Upgradation and modernisation of fider approach to Selep WTP, Gangtok 203.00 25.10.08   25% 50.00 50.00 153.00 Work Under Progress
8 Augmentation of Ranipool Bazar Water Supply  Scheme 394.00  --- 31.3.2009 59% 186.32 186.32 207.68 Work Under Progress
9 Augmentation of Ranipool Bazar Water Supply  Scheme 394.00  --- 31.3.2009 59% 186.32 186.32 207.68 Work Under Progress
10 Beautification and boundary fencing at Ridge Park Gangtok 40.00  ---  --- 100% 16.00 16.00 24.00 Work Under Progress
  Total ::: 3119.27       1817.23 1817.23 868.04  
  CIVIL DEPOSIT            
1 Water Supply Scheme for Industrial Growth Centre at Samlik Marchak 320.73 08.01.2007 08.01.2008 81% 266.53 266.53 54.20 Work under Progress  
  Fund transfer from Police Deptt                
1 Providing W/S to IRB at Pipaley, West Sikkim 85.00  ---  --- 100% 85.00 85.00 0.00 Work under Progress
  Fund transfer from Industry Deptt                
1 Setting of sewerage system i/c construction of sewerate treatment plant for Indo China trade Mart, Sherathang, East Sikkim 261.00  ---  --- 30% 0.00 0.00 261.00 Agreement process to HO
  Total :: 320.73       266.53 266.53 54.20  
  State Plan : 4215-02-106-34-34.00.72 - Construction of Drainage           
  and Sewerage System at Gangtok.          
1 Construction of Maintenance store shed at Adampool 9.55 24.05.05 23.09.06 100% 8.00 8.00 1.55 Work completed
2 Extension of Gangtok Sewerage System to Lower Sundergoan, Tadong 8.17 08.10.05 07.12.05 100% 8.03 8.03 0.14 Work completed
3 Extension of Gangtok Sewerage System to Vetenary Complex above Krishi Bhawan, Tadong 5.49  ---  --- 100% 5.26 5.26 0.23 Work Completed.
4 Rehabilitation of sewer submain above EP Church to Boys Hostel, Dara Goan Tadong 11.34  ----  ---- 100% 2.50 2.50 8.84 Work Completed.
5 Replacement of existing sewer sub main at Tadong near SSI 6.15  ---  ---  - 0.00 0.00 6.15 To be tendered
6 Surface improvement, drainage & protective works in STP Complex, Adampool, East Sikkim 19.95  ---  --- 10% 0.00 0.00 19.95 Work under progress
  Total :  60.65       23.79 23.79 36.86  
(Rs. in lakhs)  
Sl Name of Schemes Total Date of Target Progress   Grand Balance If project is behind
No.   Sanctioned Commence- Date of Physical Financial Total fund schedule resons
    Cost ment Completion in % (Rs. Edpdt. ruquired thereof /
    (Rs.in lakhs)       in lakhs)   (Rs.in lakhs) Remarks
1 2 4 5 6 7 8 9 10 11
  2215-01-101-60-45-72 Mtc. W/S/S (Plan)                
1 Const. of Chowkidar Qtr & Control Room Near Mintokgang 6.63 29/2/08  -- 77% 3.11 3.11 3.52 Work under progress  
2 Retoration work at Km 5th - 6th, Chain 1 Rateychu 8.21 7.3.08 26.6.08 100% 8.21 8.21 0.00 Work Completed.  
3 Renovation of Northern jhora at Selep 6.26  --  --- 100% 0.00 0.00 6.26 Work under progress
4   6.26  --  --- 100% 0.00 0.00 6.26 Work under progress
  Total :: 21.10       11.32 11.32 9.78  
  4215-01-101-60-60-00-71 Gangtok W/S/S (State Plan)                
1 Renovation of 10 lacs gallon reservoir at Selep 28.40     75% 0.00 0.00 28.40 Work under progress
2 Improvement of security fencing at water treatment plant at selep 27.69     100% 27.20 27.20 0.49 Work Completed.
3 Replacement of old and rusted pipe & fittings for SAP camp, Pangthang 5.93     100% 5.93 5.93 0.00 Work Completed.
4 Const. of 35,000 gallon reservoir and control room at Development Area 11.89 20/2/08 20/4/08 75% 0.00 0.00 11.89 Work under progress
5 Brick fencing around 85000 gallon tank at Tadong 5.41  --  --- 60% 0.00 0.00 5.41 Work under progress
6 Brick compound wall at Enchey Control Room 4.02 10.11.08  --- 100% 0.00 0.00 4.02 Work Completed.
  Total :: 83.34       33.13 33.13 50.21  
  4215-01-102-34-46-71(P) WSS in RMC                
1 Replacement of main trunk line & ext.of distb.system in Pelling Rabdentse W/S/S 35.67 15.8.2001 14.7.2002 100% 32.02 32.02 3.65 Work completed & final bill closed, STCS final bill pending
2 Augmentation of Sombaria W/S/S 19.64 29.2.2006 29.5.2006 100% 18.47 18.47 1.17 Work completed 
3 Providing W/S/S to Baigunay in West Sikkim 8.73     30% 0.00 0.00 8.73 Work under progress
4 Const. of 1 lakh ltr RCC reservoir and hydrant for Rinchenpong Gumpa in West Sikkim 9.37 22.2.2008 21.8.2008 75% 3.86 3.86 5.51 Work under progress
  Total :: 73.41       54.35 54.35 19.06  
  MJ. HD: JNNURM            
1 Rehabilitation of Sewer main line along M.G. Marg, New Market & Tibet Road, Gangtok 309.00 25/9/07 24/11/07 100% 303.98 303.98 5.02 Work under progress 309
2 Rehabilitation of Sewer main line along National Highway to Adampool 1556.25  ---  --- 80% 982.66 982.66 573.59 Work under progress 1556.3
3 Extn. Of sewerage system below NH Way 5th & 6th mile, Gtk - Ranipool Road (area covered Lumsay, Upper Samdur to STP, Break Pressure Tank) Plase I 526.76  ---  --- 35% 25.05 25.05 501.71 Work under progress
4 Extn. of sewerage system below NH Way 5th & 6th mile, Gtk - Ranipool Road (area covered Lumsay, Upper Samdur to STP, Break Pressure Tank) Phase II 526.76  ---  --- 30% 52.64 52.64 474.12 Work under progress
  Total :: 2918.77       1364.33 1364.33 1554.44  
  (Rs. in lakhs)  
  Name of Schemes Total Date of Target Progress   Grand Balance If project is behind
Sl   Sanctioned Commence- Date of Physical Financial Total fund schedule resons
No.   Cost ment Completion in % (Rs. Edpdt. ruquired thereof /
    (Rs.in lakhs)       in lakhs)   (Rs.in lakhs) Remarks
  4215- NRCP                
1 Extension of sewerage system to Pani house Area, Gangtok. 81.81 2005 2007 100% 81.81 81.81 0.00 work completed 
2 Extension of sewerage system to VIP Colony and Rajbhavan,Gangtok. 208.67  -do-  -do- 100% 208.67 208.67 0.00 work completed 
3 Extension of sewerage system to Arithang, Gangtok. 163.60  -do-  -do- 100% 163.60 163.60 0.00 work completed
4 Extension of sewerage system TO Development Area, Gangtok. 62.42  -do-  -do- 100% 62.42 62.42 0.00 work completed
5 Extension of sewerage system Tadong. 169.81  -do-  -do- 100% 169.28 169.28 0.53 Work completed.
6 Extension of sewerage system below Vajra hall, Baluwakkhani and  Taxi stand Sichey (52.28+21.02) 79.30  -do-  -do- 100% 79.30 79.30 0.00 Work completed.
7 Extension of sewerage system TO Lamichaney Gaon 6th mile , Tadong         (Part - I).                                                     Mrs. Tulshi Devi Chettri                        100%       Work completed
8 Extension of sewerage system TO Lamichaney Gaon 6th mile , Tadong                                                 ( Part -II).                                                               Deo Maya Gurung       100%       Work completed
9 Extension of sewerage system near residence of Sonam Gyatso at 6th mile, Tadong.  Mrs.  Pushpa Mangar       100%       work completed
10 Extension of sewerage system below  Rajen Sharma residence at Daragaon, Tadong.        100%       Work completed
11 Diversion of ewerage system below Hotel Madhuban to PNG School approach footpath, Dev. Area, Gangtok.                  Mr. Pempa Bhutia       100%       Work completed
12 Extension of sewerage system below church, Arithang, Gangtok.   Marina Alley       100%       Work completed
13 Extension of sewerage system below Tamang Gumpa complex, Sichey, Gangtok.               Work completed
14 Extension of sewerage system to Enchey compound, Gangtok (Phase II).                           Mr. Champa Choden               Work completed
15 Extension of sewerage system along Rajya Sainik jhora, PS Road, Gangtok.               Work completed
16 Extension of sewerage system below Arithang Gumpa,Arithang.               Work completed
  TOTAL  (Sl.No. 1 to 16) 95.39       95.39 95.39 0.00  
(Rs. in lakhs)  
  Name of Schemes Total Date of Target Progress   Grand Balance If project is behind
Sl   Sanctioned Commence- Date of Physical Financial Total fund schedule resons
No.   Cost ment Completion in % (Rs. Edpdt. ruquired thereof /
    (Rs.in lakhs)       in lakhs)   (Rs.in lakhs) Remarks
  2 4 5 6 7 8 9 10 11
1 Extension of sewerage system to Phewa busty below NH-31, Tadong.                    Mr. Tashi Bhutia               Work delay due to monsoon
2 Extension of sewerage system to ICAR area near Agriculture office, Tadong (Pt. II).   Mrs. Tulshi Devi Chettri               Work completed
3 Extension of sewerage system below Convoy Ground, Tadong.                           Mr. Nayan Tshering               Work delay due to monsoon
4 Extension of sewerage system below NH-31, Krishi Bhavan, Tadong.                            Mr. Bilta Rai               Work completed final bill under process
5 Extension of sewerage system to Bhanugram below DPH, Gangtok.               Mr. Kumar Lama               Work completed
6 Extension of sewerage system along Hamro Garage jhora, Arithang to Indira Bye Pass road, Sichey, Gangtok.                               Mr. Norbu Gurung               Work completed
7 Providing River Training works and improvement works at STP complex, Adampool ( Part-I, II & III).                         Mr. Pravin Agarwal               Work under progress
8 Construction of Recreational Park at STP complex, Adampool uncer State Green Mission Concept.               Work completed
9 Extension of sewerage system to Lower Kazi Road area, Gangtok.                         Mrs.  Samita Sharma               Work completed 
10 Extension of sewerage system from Women's Hostel to Deorali School road, Deorali.     Mr. Mingma Bhutia               Work completed
11 Extension of sewerage system below TNHS School road near Mandar Lodge, Dev. Area, Gangtok.               Work order to be issued
12 Extension of sewerage system below Laxmi Cottage, Lower Arithang.                          Mrs. Rajni Gurung               Work completed
13 Extension of sewerage systen nearby residence of Mr. Chewang Bhutia above Tadong Bazar               Work under progress
14 Extension of sewerage system from Mintokgang area to MLA Hostel via Samman Bhavan, Gangtok.               Work under progress
15 Extension of sewerage system below lall Bazar area to maint trunk lines along NH- Way above Tenzing & Tenzing, Gangtok.               Objection fro land owner.
(Rs. in lakhs)  
  Name of Schemes Total Date of Target Progress   Grand Balance If project is behind
Sl   Sanctioned Commence- Date of Physical Financial Total fund schedule resons
No.   Cost ment Completion in % (Rs. Edpdt. ruquired thereof /
    (Rs.in lakhs)       in lakhs)   (Rs.in lakhs) Remarks
  2 4 5 6 7 8 9 10 11
16 Extension of sewerage system near EP Church Tadong.               Work completed
17 Extension of sewerage system to Baral Gaon (Part - II 'B')               Work under progress
18 Extension of sewerage system to Baral Gaon (Part - II 'A')               Work under progress
19 Extension of sewerage system below Rahul Tyres below NH-31A nearby inspection bunglow, Tadong.               Work under progress
20 Extension of sewerage system along STNM jhora, Gangtok.               Work completed
  TOTAL  276.75       274.20 274.20 2.55  
21 Pipe Component         0.00 29.98    
22 Preparation of DPR 8.27       8.27 8.27 0.00  
23 Consultancy services for finalization of technology for preparation of NIT for construction of 8mld STP,Adampool. 11.98     100% 12.52 12.52 -0.54  
24 Construction Of  8MLD Sewage Treatment Plant at Adampool. 405.00     97% 372.35 372.35 32.65  
25 Revised cost of the schame of Gangtok sewerage system 8MLD STP at Adampool 136.00     0% 29.19 29.19 106.81  
26 Difference in cost of materials on contract works 2.58       2.58 2.58 0.00  
27 Difference in cost of materials 6.49       6.49 6.49 0.00  
  TOTAL I 570.32       431.40 461.38 138.92  
  GRAND TOTAL::::  1708.07       1566.07 1596.05 112.02  
  NRCD                
1 Preparation of DPR of six towns 65.00  --  -- 100% 50.50 50.50 14.50  
2 Setting up sewer facility including STP at Ranipool 590.24  --  -- 75% 332.76 332.76 257.48 Work under process
3 Seting up Sewer System in & around Rangpo. 494.00     0% 0.00 0.00 494.00 Work under process
4 Setting up Sewer System in and around Singtam Bazar East Sikkim 483.57  --  -- 60% 290.05 210.00 273.57 Work under process
5 Setting of sewerage facility i/c STP at Namchi Town and its surrounding areas. 1097.64 ------ ------ 20% 50.00 50.00 1047.64 Work under Progress
6 Setting of sewerage facility i/c STP at Melli Town and its surrounding areas. 341.00 ------ ------ 40% 0.00 0.00 341.00 Work under Progress
7 Setting of sewerage facility i/c STP at Jorethang Town and its surrounding areas. 480.00 ------ ------ 5% 0.00 0.00 480.00 Materials yet to received
  TOTAL :: 1632.81       673.31 593.26 1039.55  
  UIDSMT                
1 Augmentation of Mangan Water Supply North Sikkim 1582.00 26.09.08 16.09.09 35% 941.30 479.09 1102.91 Work under process
  ACA                
3 Augmentation of Yangang Bazar Water Supply  Scheme 967.27  ---  --- 30% 266.19 266.19 701.08 Work Under Progress
  (Rs. in lakhs)  
  Name of Schemes Total Date of Target Progress   Grand Balance If project is behind
Sl   Sanctioned Commence- Date of Physical Financial Total fund schedule resons
No.   Cost ment Completion in % (Rs. Edpdt. ruquired thereof /
    (Rs.in lakhs)       in lakhs)   (Rs.in lakhs) Remarks
  TSP                
1 Const. of 1 lakh ltrs Reservoir tank at Tashiding Gumpa 11.52 5.04.08 14.10.08 45% 0.00 0.00 11.52 Work under progress
2 Replacement of  50mm dia G.I. pipe, source development work Jaubari in West Sikkim 11.86  --  -- 20% 6.94 9.94 1.92 Work under progress
3 Shifting & replacement of pipes for Soreng W/S/S 6.36  --  -- 85% 5.53 5.53 0.83 Work likely to be completed
4 Replacement of 100mm dia G.I. pipe between lower Changey Source to Byadong R/Tank 41.92  --  -- 90% 41.92 41.92 0.00 Work completed 
5 Restoration of raw water mains of Gangtok Water Supply Scheme at Rateychu 8.97  --  -- 100% 8.61 8.61 0.36 Work completed
6 Permanent restoration work at  (Km 9th, ch. 22) at Rateychu (Part A) 5.33  --  -- 70% 0.00 0.00 5.33 Work under progress
7 Permanent restoration work at  (Km 13th, ch. 22) at Rateychu (Part B) 9.99  --  -- 100% 9.54 9.54 0.45 Work completed 
8 Renovation & development of existing site Engineer & staff quarter at Selep Water Treatment Plant 31.29  --  -- 0% 0.00 0.00 31.29 Put to tender
  TOTAL :: 127.23       72.54 75.54 51.69  
 
 
 
 
 
 
               (T.B. Gurung)
Additional Chief Engineer
W.S. & PHE Department.