|
|
JULY 2009 Monthly Progress Report |
|
|
|
|
|
(Rs. in lakhs) |
|
|
|
|
Sl |
Name of Schemes |
Total |
Date of |
Target |
Progress |
|
Grand |
Balance |
If project is behind |
|
|
No. |
|
Sanctioned |
Commence- |
Date of |
Physical |
Financial |
Total |
fund |
schedule resons |
|
|
|
|
Cost |
ment |
Completion |
in % |
(Rs. |
Edpdt. |
ruquired |
thereof / |
|
|
|
|
(Rs.in lakhs) |
|
|
|
in lakhs) |
|
(Rs.in lakhs) |
Remarks |
|
|
1 |
2 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
|
|
|
NABARD SCHEMES |
|
|
|
|
|
|
|
|
|
|
1 |
Augmentation of Tashiding Bazar
Water Supply Scheme |
261.21 |
15.12.07 |
14.12.08 |
70% |
136.12 |
136.12 |
125.09 |
Work under Progress |
|
|
2 |
Augmentation.of Hee Bermiok
Bazar Water Supply Scheme |
102.00 |
10.9.07 |
9.03.07 |
88% |
70.40 |
70.40 |
31.60 |
Work under Progress |
|
|
3 |
Improvement of intake
structure, shifting and replacement of 4" dia GI Pipe line from Rehsi
Khola source for Kaluk - Rinchenpong W/S/S |
79.83 |
1.08.07 |
31.1.08 |
100% |
80.23 |
80.23 |
-0.40 |
Work Completed |
|
|
4 |
Construction of Sedimentation
Tank at Naya Bazar W/S Scheme |
22.92 |
6.9.07 |
7.6.08 |
98% |
15.21 |
15.21 |
7.71 |
Work under Progress |
|
|
5 |
Augmentation of Mangalbaria W/S
Scheme in West Sikkim |
258.98 |
6.4.07 |
29.12.08 |
80% |
189.23 |
189.23 |
69.75 |
Work under Progress |
|
|
6 |
Augmentation of Reshi Water
Supply Scheme |
264.00 |
-- |
-- |
10% |
28.91 |
28.91 |
|
Work under Progress |
|
|
7 |
Providing W/S to Debrung,
Dhambudara and Kamrang in Namchi |
220.58 |
------ |
------ |
10% |
15.00 |
15.00 |
205.58 |
Work under Progress |
|
|
8 |
Providing 2 unit gravity
pressure filter & re-alignment of dist.line for Charcharey source, Jorethang W/S System |
53.58 |
------ |
------ |
25% |
17.14 |
17.14 |
36.44 |
Work under Progress |
|
|
9 |
Augmentation.of Darap Water
Supply Scheme, West Sikkim |
246.60 |
|
|
10% |
0.00 |
0.00 |
246.60 |
Work under Progress |
|
|
10 |
Augmentation of Rangpo W/S by
lifting from Rangpo Khola |
135.58 |
6/2/2002 |
9/2/2005 |
60% |
98.63 |
98.63 |
36.95 |
Work held up due to washout of the
site & materials by flood of Rangpo Khola |
|
|
11 |
Const. of 198cum reservoir
above Milk Dairy 5th Mile, Tadong |
10.12 |
6/8/2007 |
9/7/2007 |
97% |
2.75 |
7.36 |
2.76 |
Work under Progress |
|
|
12 |
Rorathang Water Supply Scheme
in East Sikkim |
520.35 |
8.9.08 |
7.9.2010 |
48% |
70.43 |
70.43 |
449.92 |
Work under Progress |
|
|
|
13 |
Augmentation of Singtam(RMC)
W/S Scheme in East Sikkim |
459.62 |
18.4.08 |
12.4.09 |
75% |
420.99 |
420.99 |
38.63 |
Work under Progress |
|
|
|
14 |
Const. of W/S Scheme at Middle
Camp in East Sikkim |
319.51 |
|
|
|
72.26 |
72.26 |
247.25 |
Work under Progress |
|
|
|
15 |
Const. of W/S Scheme at Shekwa
Bazar in East Sikkim |
76.15 |
|
|
|
11.52 |
11.52 |
64.63 |
Work under Progress |
|
|
|
|
Total ::: |
2635.37 |
|
|
|
1145.04 |
1149.65 |
1250.63 |
|
|
|
|
|
B.A.D.P. SCHEMES |
|
|
|
|
|
|
|
|
|
|
1 |
Providing Water Supply to Trade
Mart at Sherathang |
338.00 |
16.4.2007 |
15.3.2007 |
100% |
61.78 |
61.78 |
276.22 |
Work completed |
|
|
|
3 |
Augmentation of Bitchu Water
Supply Scheme |
50.00 |
18.4.2007 |
17.4.2008 |
90% |
47.76 |
47.76 |
2.24 |
Work under progress |
|
|
|
4 |
Augmentation of Drinking W/S at
Lachung, North Sikkim |
358.00 |
24.7.07 |
23.10.07 |
95% |
295.52 |
343.58 |
14.42 |
Work under progress |
|
|
|
5 |
Augmentation of Yuksum Water Supply Scheme. |
150.00 |
9.9.2005 |
1.7.2007 |
100% |
141.12 |
141.12 |
8.88 |
Work completed |
|
|
|
|
Total ::: |
896.00 |
|
|
|
546.18 |
594.24 |
301.76 |
|
|
|
|
|
NLCPR SCHEMES |
|
|
|
|
|
|
|
|
|
|
1 |
Augmentation of
Gyalshing Water Supply Scheme. |
752.28 |
10.01.2005 |
31.03.2007 |
99% |
712.85 |
712.85 |
39.43 |
Work under Progress, likely to be
completed |
|
|
2 |
Augmentation of W/S Scheme for greater Rangpo in East Sikkim |
1699.95 |
25.4.2007 |
24.4.2008 |
83% |
1694.20 |
1694.20 |
5.75 |
Work Under Progress |
|
|
3 |
Construction of Water Supply Scheme at Sang Naya Bazar |
206.72 |
---- |
---- |
50% |
119.83 |
131.32 |
75.40 |
Work Under Progress |
|
|
4 |
Augmentation of Rhenock W/S Scheme in East Sikkim |
1627.31 |
12.9.08 |
11.9.2010 |
30% |
681.60 |
681.60 |
945.71 |
Work Under Progress |
|
|
|
Total ::: |
4286.26 |
|
|
|
3208.48 |
3219.97 |
1066.29 |
|
|
|
(Rs. in lakhs) |
|
|
|
|
Sl |
Name of Schemes |
Total |
Date of |
Target |
Progress |
|
Grand |
Balance |
If project is behind |
|
|
No. |
|
Sanctioned |
Commence- |
Date of |
Physical |
Financial |
Total |
fund |
schedule resons |
|
|
|
|
Cost |
ment |
Completion |
in % |
(Rs. |
Edpdt. |
ruquired |
thereof / |
|
|
|
|
(Rs.in lakhs) |
|
|
|
in lakhs) |
|
(Rs.in lakhs) |
Remarks |
|
|
1 |
2 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
|
|
|
NEC SCHEMES |
|
|
|
|
|
|
|
|
|
|
1 |
Kaluk - Rinchenpong W/S Scheme. |
350.00 |
10.2.2004 |
31.03.2007 |
100% |
346.47 |
346.47 |
3.53 |
Work completed |
|
|
2 |
Providing distribution Reservoir & distribution main trunk lines for Namchi W/S System to Namchi Town. |
432.76 |
17.11.2006 |
16.5.2007 |
100% |
351.64 |
351.64 |
81.12 |
Work completed |
|
|
3 |
Const. of security fencing approach road, parking yard
compound lighting at Selep WTP |
211.79 |
10.2.2004 |
--- |
100% |
201.67 |
201.67 |
10.12 |
Work completed, final payment to
be made |
|
|
4 |
Extension of sewerage system in and around Gangtok, Phase -
III |
420.51 |
10.2.2004 |
--- |
100% |
399.64 |
399.64 |
20.87 |
Work completed, final payment to
be made |
|
|
5 |
Providing new distribution network system for W/S to Namchi
town PH-II |
443.50 |
--- |
--- |
35% |
53.98 |
53.98 |
389.52 |
Work Under Progress |
|
|
6 |
Strengthening of Distribution system of Pakyong W/S in East
Sikkim. |
229.71 |
10.8.2006 |
12.2.2007 |
100% |
227.51 |
227.51 |
2.20 |
Work completed |
|
|
7 |
Upgradation and modernisation of fider approach to Selep WTP,
Gangtok |
203.00 |
25.10.08 |
|
25% |
50.00 |
50.00 |
153.00 |
Work Under Progress |
|
|
8 |
Augmentation of Ranipool Bazar Water Supply Scheme |
394.00 |
--- |
31.3.2009 |
59% |
186.32 |
186.32 |
207.68 |
Work Under Progress |
|
|
9 |
Augmentation of Ranipool Bazar Water Supply Scheme |
394.00 |
--- |
31.3.2009 |
59% |
186.32 |
186.32 |
207.68 |
Work Under Progress |
|
|
10 |
Beautification and boundary fencing at Ridge Park Gangtok |
40.00 |
--- |
--- |
100% |
16.00 |
16.00 |
24.00 |
Work Under Progress |
|
|
|
|
Total ::: |
3119.27 |
|
|
|
1817.23 |
1817.23 |
868.04 |
|
|
|
|
CIVIL DEPOSIT |
|
|
|
|
|
|
|
|
|
|
|
1 |
Water Supply Scheme for Industrial Growth Centre at Samlik
Marchak |
320.73 |
08.01.2007 |
08.01.2008 |
81% |
266.53 |
266.53 |
54.20 |
Work under Progress |
|
|
|
|
Fund transfer from Police Deptt |
|
|
|
|
|
|
|
|
|
|
1 |
Providing W/S to IRB at
Pipaley, West Sikkim |
85.00 |
--- |
--- |
100% |
85.00 |
85.00 |
0.00 |
Work under Progress |
|
|
|
Fund transfer from Industry
Deptt |
|
|
|
|
|
|
|
|
|
|
1 |
Setting of sewerage system i/c
construction of sewerate treatment plant for Indo China trade Mart,
Sherathang, East Sikkim |
261.00 |
--- |
--- |
30% |
0.00 |
0.00 |
261.00 |
Agreement process to HO |
|
|
|
Total :: |
320.73 |
|
|
|
266.53 |
266.53 |
54.20 |
|
|
|
|
|
State Plan : 4215-02-106-34-34.00.72 - Construction of
Drainage |
|
|
|
|
|
|
|
|
|
|
|
|
and Sewerage System at Gangtok. |
|
|
|
|
|
|
|
|
|
|
|
1 |
Construction of Maintenance store shed at Adampool |
9.55 |
24.05.05 |
23.09.06 |
100% |
8.00 |
8.00 |
1.55 |
Work completed |
|
|
|
2 |
Extension of Gangtok Sewerage System to Lower Sundergoan,
Tadong |
8.17 |
08.10.05 |
07.12.05 |
100% |
8.03 |
8.03 |
0.14 |
Work completed |
|
|
|
3 |
Extension of Gangtok Sewerage System to Vetenary Complex
above Krishi Bhawan, Tadong |
5.49 |
--- |
--- |
100% |
5.26 |
5.26 |
0.23 |
Work Completed. |
|
|
|
4 |
Rehabilitation of sewer submain above EP Church to Boys
Hostel, Dara Goan Tadong |
11.34 |
---- |
---- |
100% |
2.50 |
2.50 |
8.84 |
Work Completed. |
|
|
|
5 |
Replacement of existing sewer sub main at Tadong near SSI |
6.15 |
--- |
--- |
- |
0.00 |
0.00 |
6.15 |
To be tendered |
|
|
|
6 |
Surface improvement, drainage & protective works in STP
Complex, Adampool, East Sikkim |
19.95 |
--- |
--- |
10% |
0.00 |
0.00 |
19.95 |
Work under progress |
|
|
|
|
Total : |
60.65 |
|
|
|
23.79 |
23.79 |
36.86 |
|
|
|
|
|
(Rs. in lakhs) |
|
|
|
|
|
Sl |
Name of Schemes |
Total |
Date of |
Target |
Progress |
|
Grand |
Balance |
If project is behind |
|
|
|
No. |
|
Sanctioned |
Commence- |
Date of |
Physical |
Financial |
Total |
fund |
schedule resons |
|
|
|
|
|
Cost |
ment |
Completion |
in % |
(Rs. |
Edpdt. |
ruquired |
thereof / |
|
|
|
|
|
(Rs.in lakhs) |
|
|
|
in lakhs) |
|
(Rs.in lakhs) |
Remarks |
|
|
|
1 |
2 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
|
|
|
|
2215-01-101-60-45-72 Mtc. W/S/S (Plan) |
|
|
|
|
|
|
|
|
|
|
|
1 |
Const. of Chowkidar Qtr & Control Room Near Mintokgang |
6.63 |
29/2/08 |
-- |
77% |
3.11 |
3.11 |
3.52 |
Work under progress |
|
|
|
2 |
Retoration work at Km 5th - 6th, Chain 1 Rateychu |
8.21 |
7.3.08 |
26.6.08 |
100% |
8.21 |
8.21 |
0.00 |
Work Completed. |
|
|
|
3 |
Renovation of Northern jhora at Selep |
6.26 |
-- |
--- |
100% |
0.00 |
0.00 |
6.26 |
Work under progress |
|
|
|
4 |
|
6.26 |
-- |
--- |
100% |
0.00 |
0.00 |
6.26 |
Work under progress |
|
|
|
|
Total :: |
21.10 |
|
|
|
11.32 |
11.32 |
9.78 |
|
|
|
|
|
4215-01-101-60-60-00-71 Gangtok W/S/S (State Plan) |
|
|
|
|
|
|
|
|
|
|
|
1 |
Renovation of 10 lacs gallon reservoir at Selep |
28.40 |
|
|
75% |
0.00 |
0.00 |
28.40 |
Work under progress |
|
|
|
2 |
Improvement of security fencing at water treatment plant at
selep |
27.69 |
|
|
100% |
27.20 |
27.20 |
0.49 |
Work Completed. |
|
|
|
3 |
Replacement of old and rusted pipe & fittings for SAP
camp, Pangthang |
5.93 |
|
|
100% |
5.93 |
5.93 |
0.00 |
Work Completed. |
|
|
|
4 |
Const. of 35,000 gallon reservoir and control room at
Development Area |
11.89 |
20/2/08 |
20/4/08 |
75% |
0.00 |
0.00 |
11.89 |
Work under progress |
|
|
|
5 |
Brick fencing around 85000 gallon tank at Tadong |
5.41 |
-- |
--- |
60% |
0.00 |
0.00 |
5.41 |
Work under progress |
|
|
|
6 |
Brick compound wall at Enchey Control Room |
4.02 |
10.11.08 |
--- |
100% |
0.00 |
0.00 |
4.02 |
Work Completed. |
|
|
|
|
Total :: |
83.34 |
|
|
|
33.13 |
33.13 |
50.21 |
|
|
|
|
|
4215-01-102-34-46-71(P) WSS in RMC |
|
|
|
|
|
|
|
|
|
|
|
1 |
Replacement of main trunk line & ext.of distb.system in
Pelling Rabdentse W/S/S |
35.67 |
15.8.2001 |
14.7.2002 |
100% |
32.02 |
32.02 |
3.65 |
Work completed & final bill
closed, STCS final bill pending |
|
|
|
2 |
Augmentation of Sombaria W/S/S |
19.64 |
29.2.2006 |
29.5.2006 |
100% |
18.47 |
18.47 |
1.17 |
Work completed |
|
|
|
3 |
Providing W/S/S to Baigunay in West Sikkim |
8.73 |
|
|
30% |
0.00 |
0.00 |
8.73 |
Work under progress |
|
|
|
4 |
Const. of 1 lakh ltr RCC reservoir and hydrant for
Rinchenpong Gumpa in West Sikkim |
9.37 |
22.2.2008 |
21.8.2008 |
75% |
3.86 |
3.86 |
5.51 |
Work under progress |
|
|
|
|
Total :: |
73.41 |
|
|
|
54.35 |
54.35 |
19.06 |
|
|
|
|
|
MJ. HD: JNNURM |
|
|
|
|
|
|
|
|
|
|
|
1 |
Rehabilitation of Sewer main line along M.G. Marg, New Market
& Tibet Road, Gangtok |
309.00 |
25/9/07 |
24/11/07 |
100% |
303.98 |
303.98 |
5.02 |
Work under progress |
309 |
|
|
2 |
Rehabilitation of Sewer main line along National Highway to
Adampool |
1556.25 |
--- |
--- |
80% |
982.66 |
982.66 |
573.59 |
Work under progress |
1556.3 |
|
|
3 |
Extn. Of sewerage system below NH Way 5th & 6th mile, Gtk
- Ranipool Road (area covered Lumsay, Upper Samdur
to STP, Break Pressure Tank) Plase I |
526.76 |
--- |
--- |
35% |
25.05 |
25.05 |
501.71 |
Work under progress |
|
|
|
4 |
Extn. of sewerage system below NH Way 5th & 6th mile, Gtk
- Ranipool Road (area covered Lumsay, Upper Samdur
to STP, Break Pressure Tank) Phase II |
526.76 |
--- |
--- |
30% |
52.64 |
52.64 |
474.12 |
Work under progress |
|
|
|
|
Total :: |
2918.77 |
|
|
|
1364.33 |
1364.33 |
1554.44 |
|
|
|
|
|
|
(Rs. in lakhs) |
|
|
|
|
|
|
Name of Schemes |
Total |
Date of |
Target |
Progress |
|
Grand |
Balance |
If project is behind |
|
|
|
Sl |
|
Sanctioned |
Commence- |
Date of |
Physical |
Financial |
Total |
fund |
schedule resons |
|
|
|
No. |
|
Cost |
ment |
Completion |
in % |
(Rs. |
Edpdt. |
ruquired |
thereof / |
|
|
|
|
|
(Rs.in lakhs) |
|
|
|
in lakhs) |
|
(Rs.in lakhs) |
Remarks |
|
|
|
|
4215- NRCP |
|
|
|
|
|
|
|
|
|
|
|
1 |
Extension of sewerage system to
Pani house Area, Gangtok. |
81.81 |
2005 |
2007 |
100% |
81.81 |
81.81 |
0.00 |
work completed |
|
|
|
2 |
Extension of sewerage system to
VIP Colony and Rajbhavan,Gangtok. |
208.67 |
-do- |
-do- |
100% |
208.67 |
208.67 |
0.00 |
work completed |
|
|
3 |
Extension of sewerage system to
Arithang, Gangtok. |
163.60 |
-do- |
-do- |
100% |
163.60 |
163.60 |
0.00 |
work completed |
|
|
4 |
Extension of sewerage system TO
Development Area, Gangtok. |
62.42 |
-do- |
-do- |
100% |
62.42 |
62.42 |
0.00 |
work completed |
|
|
5 |
Extension of sewerage system
Tadong. |
169.81 |
-do- |
-do- |
100% |
169.28 |
169.28 |
0.53 |
Work completed. |
|
|
6 |
Extension of sewerage system
below Vajra hall, Baluwakkhani and
Taxi stand Sichey (52.28+21.02) |
79.30 |
-do- |
-do- |
100% |
79.30 |
79.30 |
0.00 |
Work completed. |
|
|
7 |
Extension of sewerage system TO
Lamichaney Gaon 6th mile , Tadong
(Part - I).
Mrs. Tulshi Devi Chettri |
|
|
|
100% |
|
|
|
Work completed |
|
|
8 |
Extension of sewerage system TO
Lamichaney Gaon 6th mile , Tadong
( Part -II).
Deo Maya Gurung |
|
|
|
100% |
|
|
|
Work completed |
|
|
9 |
Extension of sewerage system
near residence of Sonam Gyatso at 6th mile, Tadong. Mrs.
Pushpa Mangar |
|
|
|
100% |
|
|
|
work completed |
|
|
10 |
Extension of sewerage system
below Rajen Sharma residence at
Daragaon, Tadong. |
|
|
|
100% |
|
|
|
Work completed |
|
|
11 |
Diversion of ewerage system
below Hotel Madhuban to PNG School approach footpath, Dev. Area,
Gangtok. Mr. Pempa
Bhutia |
|
|
|
100% |
|
|
|
Work completed |
|
|
12 |
Extension of sewerage system
below church, Arithang, Gangtok.
Marina Alley |
|
|
|
100% |
|
|
|
Work completed |
|
|
13 |
Extension of sewerage system
below Tamang Gumpa complex, Sichey, Gangtok. |
|
|
|
|
|
|
|
Work completed |
|
|
14 |
Extension of sewerage system to
Enchey compound, Gangtok (Phase II). Mr. Champa Choden |
|
|
|
|
|
|
|
Work completed |
|
|
15 |
Extension of sewerage system
along Rajya Sainik jhora, PS Road, Gangtok. |
|
|
|
|
|
|
|
Work completed |
|
|
16 |
Extension of sewerage system
below Arithang Gumpa,Arithang. |
|
|
|
|
|
|
|
Work completed |
|
|
|
TOTAL (Sl.No. 1 to 16) |
95.39 |
|
|
|
95.39 |
95.39 |
0.00 |
|
|
|
|
|
(Rs. in lakhs) |
|
|
|
|
|
Name of Schemes |
Total |
Date of |
Target |
Progress |
|
Grand |
Balance |
If project is behind |
|
|
Sl |
|
Sanctioned |
Commence- |
Date of |
Physical |
Financial |
Total |
fund |
schedule resons |
|
|
No. |
|
Cost |
ment |
Completion |
in % |
(Rs. |
Edpdt. |
ruquired |
thereof / |
|
|
|
|
(Rs.in lakhs) |
|
|
|
in lakhs) |
|
(Rs.in lakhs) |
Remarks |
|
|
|
2 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
|
|
1 |
Extension of sewerage system to
Phewa busty below NH-31, Tadong. Mr. Tashi Bhutia |
|
|
|
|
|
|
|
Work delay due to monsoon |
|
|
2 |
Extension of sewerage system to
ICAR area near Agriculture office, Tadong (Pt. II). Mrs. Tulshi Devi Chettri |
|
|
|
|
|
|
|
Work completed |
|
|
3 |
Extension of sewerage system
below Convoy Ground, Tadong. Mr. Nayan Tshering |
|
|
|
|
|
|
|
Work delay due to monsoon |
|
|
4 |
Extension of sewerage system
below NH-31, Krishi Bhavan, Tadong. Mr. Bilta Rai |
|
|
|
|
|
|
|
Work completed final bill under
process |
|
|
5 |
Extension of sewerage system to
Bhanugram below DPH, Gangtok.
Mr. Kumar Lama |
|
|
|
|
|
|
|
Work completed |
|
|
6 |
Extension of sewerage system
along Hamro Garage jhora, Arithang to Indira Bye Pass road, Sichey,
Gangtok.
Mr. Norbu Gurung |
|
|
|
|
|
|
|
Work completed |
|
|
7 |
Providing River Training works
and improvement works at STP complex, Adampool ( Part-I, II & III). Mr. Pravin Agarwal |
|
|
|
|
|
|
|
Work under progress |
|
|
8 |
Construction of Recreational
Park at STP complex, Adampool uncer State Green Mission Concept. |
|
|
|
|
|
|
|
Work completed |
|
|
9 |
Extension of sewerage system to
Lower Kazi Road area, Gangtok. Mrs. Samita Sharma |
|
|
|
|
|
|
|
Work completed |
|
|
10 |
Extension of sewerage system
from Women's Hostel to Deorali School road, Deorali. Mr. Mingma Bhutia |
|
|
|
|
|
|
|
Work completed |
|
|
11 |
Extension of sewerage system
below TNHS School road near Mandar Lodge, Dev. Area, Gangtok. |
|
|
|
|
|
|
|
Work order to be issued |
|
|
12 |
Extension of sewerage system
below Laxmi Cottage, Lower Arithang. Mrs. Rajni Gurung |
|
|
|
|
|
|
|
Work completed |
|
|
13 |
Extension of sewerage systen
nearby residence of Mr. Chewang Bhutia above Tadong Bazar |
|
|
|
|
|
|
|
Work under progress |
|
|
14 |
Extension of sewerage system
from Mintokgang area to MLA Hostel via Samman Bhavan, Gangtok. |
|
|
|
|
|
|
|
Work under progress |
|
|
15 |
Extension of sewerage system
below lall Bazar area to maint trunk lines along NH- Way above Tenzing &
Tenzing, Gangtok. |
|
|
|
|
|
|
|
Objection fro land owner. |
|
|
|
|
(Rs. in lakhs) |
|
|
|
|
|
Name of Schemes |
Total |
Date of |
Target |
Progress |
|
Grand |
Balance |
If project is behind |
|
|
Sl |
|
Sanctioned |
Commence- |
Date of |
Physical |
Financial |
Total |
fund |
schedule resons |
|
|
No. |
|
Cost |
ment |
Completion |
in % |
(Rs. |
Edpdt. |
ruquired |
thereof / |
|
|
|
|
(Rs.in lakhs) |
|
|
|
in lakhs) |
|
(Rs.in lakhs) |
Remarks |
|
|
|
2 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
|
|
16 |
Extension of sewerage system
near EP Church Tadong. |
|
|
|
|
|
|
|
Work completed |
|
|
17 |
Extension of sewerage system to
Baral Gaon (Part - II 'B') |
|
|
|
|
|
|
|
Work under progress |
|
|
18 |
Extension of sewerage system to
Baral Gaon (Part - II 'A') |
|
|
|
|
|
|
|
Work under progress |
|
|
19 |
Extension of sewerage system
below Rahul Tyres below NH-31A nearby inspection bunglow, Tadong. |
|
|
|
|
|
|
|
Work under progress |
|
|
20 |
Extension of sewerage system
along STNM jhora, Gangtok. |
|
|
|
|
|
|
|
Work completed |
|
|
|
TOTAL |
276.75 |
|
|
|
274.20 |
274.20 |
2.55 |
|
|
|
21 |
Pipe Component |
|
|
|
|
0.00 |
29.98 |
|
|
|
|
22 |
Preparation of DPR |
8.27 |
|
|
|
8.27 |
8.27 |
0.00 |
|
|
|
23 |
Consultancy services for
finalization of technology for preparation of NIT for construction of 8mld
STP,Adampool. |
11.98 |
|
|
100% |
12.52 |
12.52 |
-0.54 |
|
|
|
24 |
Construction Of 8MLD Sewage Treatment Plant at Adampool. |
405.00 |
|
|
97% |
372.35 |
372.35 |
32.65 |
|
|
|
25 |
Revised cost of the schame of
Gangtok sewerage system 8MLD STP at Adampool |
136.00 |
|
|
0% |
29.19 |
29.19 |
106.81 |
|
|
|
26 |
Difference in cost of materials
on contract works |
2.58 |
|
|
|
2.58 |
2.58 |
0.00 |
|
|
|
27 |
Difference in cost of materials |
6.49 |
|
|
|
6.49 |
6.49 |
0.00 |
|
|
|
|
TOTAL I |
570.32 |
|
|
|
431.40 |
461.38 |
138.92 |
|
|
|
|
GRAND TOTAL:::: |
1708.07 |
|
|
|
1566.07 |
1596.05 |
112.02 |
|
|
|
|
NRCD |
|
|
|
|
|
|
|
|
|
|
1 |
Preparation of DPR of six towns |
65.00 |
-- |
-- |
100% |
50.50 |
50.50 |
14.50 |
|
|
|
2 |
Setting up sewer facility
including STP at Ranipool |
590.24 |
-- |
-- |
75% |
332.76 |
332.76 |
257.48 |
Work under process |
|
|
3 |
Seting up Sewer System in &
around Rangpo. |
494.00 |
|
|
0% |
0.00 |
0.00 |
494.00 |
Work under process |
|
|
4 |
Setting up Sewer System in and
around Singtam Bazar East Sikkim |
483.57 |
-- |
-- |
60% |
290.05 |
210.00 |
273.57 |
Work under process |
|
|
5 |
Setting of sewerage facility
i/c STP at Namchi Town and its surrounding areas. |
1097.64 |
------ |
------ |
20% |
50.00 |
50.00 |
1047.64 |
Work under Progress |
|
|
6 |
Setting of sewerage facility
i/c STP at Melli Town and its surrounding areas. |
341.00 |
------ |
------ |
40% |
0.00 |
0.00 |
341.00 |
Work under Progress |
|
|
7 |
Setting of sewerage facility
i/c STP at Jorethang Town and its surrounding areas. |
480.00 |
------ |
------ |
5% |
0.00 |
0.00 |
480.00 |
Materials yet to received |
|
|
|
TOTAL :: |
1632.81 |
|
|
|
673.31 |
593.26 |
1039.55 |
|
|
|
|
UIDSMT |
|
|
|
|
|
|
|
|
|
|
1 |
Augmentation of Mangan Water
Supply North Sikkim |
1582.00 |
26.09.08 |
16.09.09 |
35% |
941.30 |
479.09 |
1102.91 |
Work under process |
|
|
|
ACA |
|
|
|
|
|
|
|
|
|
|
3 |
Augmentation of Yangang Bazar Water Supply Scheme |
967.27 |
--- |
--- |
30% |
266.19 |
266.19 |
701.08 |
Work Under Progress |
|
|
|
|
(Rs. in lakhs) |
|
|
|
|
|
Name of Schemes |
Total |
Date of |
Target |
Progress |
|
Grand |
Balance |
If project is behind |
|
|
Sl |
|
Sanctioned |
Commence- |
Date of |
Physical |
Financial |
Total |
fund |
schedule resons |
|
|
No. |
|
Cost |
ment |
Completion |
in % |
(Rs. |
Edpdt. |
ruquired |
thereof / |
|
|
|
|
(Rs.in lakhs) |
|
|
|
in lakhs) |
|
(Rs.in lakhs) |
Remarks |
|
|
|
TSP |
|
|
|
|
|
|
|
|
|
|
1 |
Const. of 1 lakh ltrs Reservoir
tank at Tashiding Gumpa |
11.52 |
5.04.08 |
14.10.08 |
45% |
0.00 |
0.00 |
11.52 |
Work under progress |
|
|
2 |
Replacement of 50mm dia G.I. pipe, source development work
Jaubari in West Sikkim |
11.86 |
-- |
-- |
20% |
6.94 |
9.94 |
1.92 |
Work under progress |
|
|
3 |
Shifting & replacement of
pipes for Soreng W/S/S |
6.36 |
-- |
-- |
85% |
5.53 |
5.53 |
0.83 |
Work likely to be completed |
|
|
4 |
Replacement of 100mm dia G.I.
pipe between lower Changey Source to Byadong R/Tank |
41.92 |
-- |
-- |
90% |
41.92 |
41.92 |
0.00 |
Work completed |
|
|
5 |
Restoration of raw water mains
of Gangtok Water Supply Scheme at Rateychu |
8.97 |
-- |
-- |
100% |
8.61 |
8.61 |
0.36 |
Work completed |
|
|
6 |
Permanent restoration work
at (Km 9th, ch. 22) at Rateychu (Part
A) |
5.33 |
-- |
-- |
70% |
0.00 |
0.00 |
5.33 |
Work under progress |
|
|
7 |
Permanent restoration work
at (Km 13th, ch. 22) at Rateychu (Part
B) |
9.99 |
-- |
-- |
100% |
9.54 |
9.54 |
0.45 |
Work completed |
|
|
8 |
Renovation & development of
existing site Engineer & staff quarter at Selep Water Treatment Plant |
31.29 |
-- |
-- |
0% |
0.00 |
0.00 |
31.29 |
Put to tender |
|
|
|
TOTAL :: |
127.23 |
|
|
|
72.54 |
75.54 |
51.69 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(T.B. Gurung) |
|
|
|
|
Additional
Chief Engineer |
|
|
|
W.S. &
PHE Department. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|